M/Y TURAMA
Rack Installation

 

The procedure consisted of:

The removal of the old 4 racks devices and cabling.
Removal of the old RF and Video cabling in the whole room and racks.
Replacement of the old analog Modulators with new Digital ones
Installation of the > 1000 meters of RF and UTP cabling within the racks.
Utilization of the racks sliding mechanism for easier access.
Installation of UPS and Network switches for easy modulator access through the network.
Fan installation for better heat dissipation.